BELLE TOWER
A building with 43-storey which is located at Rachadaphisek road, only 4-stories were constructed before the construction stopped for more than 10 years. Structural Strength Test was carried out in order to obtain the certification report of existing building structure after construction has stopped to check whether if the buidling is still viable for further construction.


Chevron Caltex
Check the label of 295 Caltex service stations, stations across the country. Ten Consultants, Inc. has been hired to perform the inspection of the label of 295 Caltex service stations, stations across the country. The height of 15 meters or more in signages were conducted in order to comply with the regulations on them scheduled to be examined.

Grand Inn Come Hotel
Building Inspection in the Grand Hotel is located on King Kaew Road, Muang District, Rachatawa City, Bangplee a 7-floor hotel has 143 rooms in a hotel with the hotel by the law number of rooms from eight to ten rooms which remained to provide for the monitoring of building rules to be established.

Building Inspection Service Honda Car Service Center Building, Sukhumvit Road
SOIL TEST & BUILDING AUDIT CO., LTD. provides building inspection services for Honda Car Service Center Building, 1 building, Sukhumvit Road, Phra Khanong Nuea Subdistrict, Watthana District, Bangkok, is classified as a service establishment with an area exceeding 2,000 square meters. According to the security weather inspection and various building equipment systems according to Section 32 bis of the Building Control Act B.E. 2522


Fire prevention and suppression system inspection Service Property Care Services (Thailand) Co., Ltd. (PCS)
SOIL TEST & BUILDING AUDIT CO., LTD. provides building and building equipment inspection services in accordance with the law to Property Care Services (Thailand) Co., Ltd. (PCS), a building with a large number of employees working inside the building, in order to ensure that the building can be used safely from fire hazards. According to the security weather inspection and various building equipment systems according to Section 32 bis of the Building Control Act B.E. 2522



Saranjai Mansion Building
SOIL TEST & BUILDING AUDIT CO., LTD. provides building inspection services for Saranjai Mansion, Sukhumvit Soi 6, Khlong Toei Subdistrict, Khlong Toei District, Bangkok, consists of 2 buildings: Building 1 and Building 2, which are 23-storey high-rise buildings. They are classified as condominiums with an area exceeding 2,000 square meters. According to the security weather inspection and various building equipment systems according to Section 32 bis of the Building Control Act B.E. 2522

STRUCTURAL STRENGTH TEST FOR SWITCHING CAPACITOR
Structural Strength Test for Switching Capacitor due to the building fire and causes structural at the third floor damaged. The building of the inspection was 3-story reinforced concrete with approximately 256 sm. The result of the inspection will be taken to analyze and assess the condition of the building structure in order to obtain the certification report of building after fire whether available for further used.

The Irish Condominium Project
SOIL TEST & BUILDING AUDIT CO., LTD. provides building inspection services for The Irish Condominium, Buildings A, B, C, E, H, 5 buildings, located on Srinakarin Road, Suan Luang Subdistrict, Suan Luang District, Bangkok. It is an 8-storey building, classified as a condominium with an area exceeding 2,000 square meters. According to the security weather inspection and various building equipment systems according to Section 32 bis of the Building Control Act B.E. 2522


Signage inspection service (Big inspection) Thai Oil Public Company Limited
Thai Oil Public Company Limited is located in Thung Sukhla Subdistrict, Sriracha District, Chonburi Province. Have trusted Ten Consultants Company Limited to provide inspection services for company Signage. Entrance area On Sukhumvit Road, 1 sign, according to building inspection as required by law.

City Apartment Building Inspection Service 9-story residential building
SOIL TEST & BUILDING AUDIT CO., LTD. provides building inspection services for City Apartment, Soi Arun Amarin 36, Arun Amarin Road. Bang Yi Khan Subdistrict, Bang Phlat District, Bangkok. It is a 9-story residential building. According to the security weather inspection and various building equipment systems according to Section 32 bis of the Building Control Act B.E. 2522

CLASS V TOWER IN SI AYUTTHAYA ROAD, BANGKOK
Structural Strength Test for 2 building was Tower A and B , these building designed for 40 storey but there are 12 storey finished constructed in building A and there are 33 storey finished constructed in building B. The Structural Strength Test of these building in order to obtain the certification report of existing building structure after stop construction whether viable for further construction.


Rajamangala National Studium Authority of Thailand
Ten Consultants Co., Ltd. in association with Building Audit Co., Ltd. were appointed by Sport Authority of Thailand (SAT), to conducted the Structural Engineering Aspects and Architectural of the building in order to improvement and repair planning. Building are reinforced concrete building and were builded over a decade.


Structural load testing of the Nestle Building.
Nestle’ (Thailand) Ltd. has an objective to use the non-operating factory in Navanakorn Industrial Estate as Raw material warehouse stock yard. The intention is to move the existing Raw material warehouse from Rama III Road to the vacant space which closer to the production plant in the Navanakorn area.

SUMMIT WINDMILL GOLF COURSE HOTEL, Bangna Trad Km 12 Samutprakarn
Summit Windmill Golf Course has planned to modify an unfinished 9 storey 5 tower building which were designed to be service apartment to turn into 5 star hotel. With this assignment, the requirement of the Static Load Capacity Test of the unfinished constructed building need to be conducted conform for the modification of the existing structure before continue construction.


Thailand Institute of Scientific and Technological Research (TISTR)
TEN has conducted the In-Situ Strength of Material test and compiled the data obtained in the calculation of the structure. Only the area that has changed the load of the 7.5 tons chamber is about 35 square meters. TEN has analyzed the stability of the structure to see if it is capable of carrying additional load or not.


Cold Storage 3,000 Tons Building Project of Unicord Public Co., Ltd.
Unicord Public Company Limited established in 1980 and dedicated it salt to product development. Unicord wishes to Renovation cold storage 3,000 Tons building to keep capacity more raw materials. The storage would ensure the security of raw material of the manufacturing process continuity.


DIOXIN ANALYTICAL LABORATORY BUILDING Ministry of Science and Technology, Department of Environmental Quality Promotion, Environmental Technology Research Center
Ten Consultants Co., Ltd. associated with United Analytical Engineering and Consultant Co., Ltd. (UAE) was appointed to conduct the Feasibility Study and Detailed Design of the first Dioxin Analytical Laboratory Building in Thailand. The site is situated at the Scientific Park, Klong 6, Rangsit – Ongkaruk Highway, Pathumthani province.

BELTON TECHNOLOGY CO., LTD. FLOOD DEFENSE PROJECT
Ten Consultants Co. , Ltd. was appointed by Belton Technology Co. , Ltd. to conduct the Feasibility Study and Detailed Design of Flood Protection System for the factory. The site is situated in Navanakorn Industrial Estate, Rangsit, Pathumthani province.

Flood Protection System Project of Ratchaburi World Cogeneration Co., Ltd.
From the big flooding over Central Region of Thailand in the year 2011, there were 7 industrial estates been flooded to the level of water height up to 2. 5-4. 0 meters. The disaster created enormous damage to all the factories in these 7 estates. Flood protection system is necessary for key organizations in the risk area such as power plant in order to prevent the enormous impact.

Le Méridien Phuket Beach Resort
Le Meridien Phuket Beach Resort Hotel is the 5 star 512 rooms located at one of the best private beach at Karon beach, Phuket island. The hotel was designed by M.L.Tri Devakul, one of the most well known architect in Thailand. The design allows all the guest room face to the sea.

Mango Tree on the river @ Yodpiman Project
MANGO TREE is Premium Thai cuisine restaurant of Coca Suki Group established for over twenty years. The newest branch of the year 2015 is Mango Tree on the river situated at Yodpimarn River Walk which is one of the best scene of consists of roof top bistro bar (4th floor), 3rd floor pub, 2nd floor cuisine restaurant, and ground floor cooking area and take away service.

PETALS INN HOTEL Sukhumvit Soi. 4, Bangkok
T. Choithram & Sons (Thailand) Co., Ltd. an international trading firm base in Dubai, United Arab Emirates having business investment and trading in more than 20 countries in 4 continents had long term developing business in Thailand over 15 years. T. Choithram & Sons had decided to renovate own trading contact office in the Sukhumvit 4 (South Nana), Sukhumvit Road in the prime area of Central Business District in Bangkok Metropolitan

Rangsit Municipality Administration Building 12 Storey Office Building Design Project
TEN Consultants Co., Ltd. was appointed by Rangsit Municipality Administration to conduct the Design of the Office building project at Rangsit - Pathumthani Road, Rangsit, Pathumthani Province. The buildings consist of 12 storey front building for office and rear building for car park, canteen and function hall on top with total gross area of 12,000 square meters.

Construction Supervision for auditorium of Engineering and Industrial Technology Faculty, Silpakorn University
TEN conducted the construction supervision for auditorium construction of Engineering and Industrial Technology Faculty, Silpakorn University where located in Praprathomchedi, Nakornprathom province.

Sport Authority of Thailand (SAT) Construction Supervision of Stadium 8 Provinces
Ten Consultants Co. , Ltd. in association with PPA Co. , Ltd. were appointed by Sport Authority of Thailand (SAT), for construction supervision of 8 provinces which are Sa-Keaw, Mahasarakham, Sakonnakorn, Samutprakarn, Amnartcharoen, Petchaboon, Narathiwat, and Saraburi.

Construction Supervision of Summit Keylex (Thailand) Co., Ltd.
Summit Keylex (Thailand) Co., Ltd. a joint venture between Summit Corporation Co., Ltd and Japan-based Keylex Corporation established to produce and dynamic automotive market with top-quality automobile and assembly parts. Sited on a land area of more than 20,000 square meters is strategically located in Hemaraj Eastern Seaboard Industrial Estate, Rayong.

Tri-wall Packaging Thai Co., Ltd. Eastern Industrial Estate, Rayong
Triwall Packaging (Thai) Co., Ltd. a joint investment of major international leader of packaging business worldwide invest in the third manufacturing plant in Thailand to be the most modern packaging technology in South East Asia. The project consists of Production building, Raw and Finish Product Warehouse, Utility Building, Office building which would be the center of training center worldwide of the group and facility support.


United Analyst and Engineering Consultant Co., Ltd. (UAE) Office and Laboratory Building Design and Construction Supervision Project
TEN Consultants Co., Ltd. was appointed by United Analyst and Engineering Consultant Co., Ltd. (UAE) to conduct the Design and Construction Management of the Office and Laboratory building project at Udomsuk Road, Sukhumvit 103, Bangkok. The building has 4 storey (provided for 7 storey expansion) with total gross area of 2,000 square meters situated in a 400 square wah land area.

Quay Wall Extension and Wharf Design Project
UNITED THAI SHIPPING CROP LIMITED., of Ten Consultants Co., Ltd. hereinafter called "TEN" to provide geotechnical investigation for the Quay Wall Extension and Wharf Design Project was performed since 23rd February 2019 and all field activities on 31st March 2019. Afterwards, the soil samples collected from investigated boreholes were delivered to laboratory and tested for their mechanical properties.

MUPA1 200MW CCPP PROJECT
Myanmar UPA Company Limited, herein also called "MUPA" engaged the services of Ten Consultants Co., Ltd., herein also called "TEN" to provide geotechnical investigation services for the MUPA1 200MW CCPP Project. TEN had mobilized equipment and crew to the project site on 19th March 2016 and commenced filed investigation since 20th March and finished the operation on the project site on 16th April 2017.

CUP-4 PROJECT
CTCI Corporation hereinafter called "CTCI" has engaged the service of Ten Consultants Co., Ltd. hereinafter called "TEN" to provide geotechnical investigation for the GPSC CUP 4 Phase 1 Project. TEN has performed his assignment since 26th December 2017 and all field activities on 18th January 2018. Afterwards, the soil samples collected from investigated boreholes were delivered to TEN's laboratory and tested for their mechanical properties.

SIPCO POWER II CCPP PROJECT
SC Engineering Co., Ltd. herein also called "SC" engaged the services of Ten Consultants Co., Ltd. herein also called "TEN" to provide. Topographic Survey for the SIPCO Power II CCPP Project (hereinafter called SPCO Project). TEN commenced his services since 13th December 2017 and finished field investigation on 26th December 2017.

Kampot Tanker Terminal (PAPA OIL) Project, Kampot province, Cambodia
TEN was engaged by MBA Engineering & Construction (CAMBODIA) Co.,Ltd to provide a service of Soil Investigation service the project area in Kampot Tanker Terminal (PAPA OIL) located in the gulf of Thailand in Kampot province, Cambodia.

Soil Thermal Resistivity & Electrical Resistivity Test for Underground Power Transmission Cable Phnom Penh, Cambodia
Nippon Koei Co., Ltd. under the JICA's grant fund engaged the services to Ten Consultants Co., Ltd. To provide Soil The rmal Resistivity & Electrical Soil Resistivity Test for Underground Power Transmission Cable Line and Distribution System Expansion Project in Phnom Penh, Cambodia.

PHNOM PENH CITY TRANSMISSION AND DISTRIBUTION SYSTEM EXPANSION PROJECT PHASE 2 Soil Thermal Resistivity Test
CHEANG ENGINEERING CONSULTANTS CO., LTD. engaged the service to Ten Consultants Co., Ltd. to provide Soil Thermal Resistivity Test Report for Phnom Penh City Transmission Cable line and Distribution System Expansion Project PHASE 2.

Nonthaburi Flood Protection Project Department of Public Works and Town & Country Planning
Department of Public Works and Town & Country Planning would had awarded contract of Survey and Detailed Design of Flood protection on the west bank of Nonthaburi province to Water Development Co., Ltd. (WDC). The project value of 44,920,000 Baht.


Geotechnical Investigation Services of CHAIYAPHUM WIND FARM PROJECT
Italthai Engineering Company Limited, herein also called "ITE" engaged the services of Ten Consultants Co., Ltd,, to provide Geotechnical Investigation Services for Chaiyaphum Wind Farm Project where located in Sap Yai district at Chaiyaphum province. TEN commenced his services by performing his field operation since 9th June 2014 and finished drilling operation on 19th June 2014.


THAI OIL NEW JETTY 7/8 EXPANSION PROJECT Subsurface under sea-bed Investigation service for Petroleum Jetty Foundation Construction
Ten Consultants Co., Ltd. was appointed by Thaioil Public Company Limited to conduct the subsurface seabed investigation service. This new petroleum jetty number 7 and 8 would be constructed to serve for the Roll-in & Roll-out of Petroleum Tanker size 3,000-50,000 Dry Weight Tonnage (DWT). The seabed soil investigation would be the information for the design of the jetty foundation.


PRIMARY ROADS RESTORATION PROJECT Contract Number 5B and 5C, CAMBODIA
The Ministry of Public Work and Transport (Cambodia) has authorized Nawarat Patanakarn Public Co., Ltd. To commission the Primary Roads Restoration Project, Contract No. 5B (Kampong Chnang-Pouthisat) and 5C (Pouthisat-Batdambang) The distance of the program is approximately 315 kilometers in total, which consist of 42 bridges located inside the route.


North Economic Corridor Project : National Highway 3 ( Houay Xay – Boten ) LAO PDR
LAO P.D.R. had granted from three source of fund i.e. Asian Development Bank (ADB), Royal Thai Government (PRC) to renovate the international highway link between Southern of China, Yunnan State - Northern LAO P.D.R. and Northern Thailand at Chiangrai Province. The project is so called Northern Economic Corridor National Highway 3 (Houay Xay - Boten)

Southern Blue Line Mass Rapid Transit Tunnel
The Construction Contract of the first Underground Mass Rapid Transit in Thailand was divided into two major contracts i.e. The Northern Line and the Southern Line. The Southern Line was awarded contract to BMCL leaded by Ch.Karnchang Public Co., Ltd. The Southern Line consists of the station from Hua-Lamphong Station to Bankai Station.

PHU HORM GAS DEVELOPMENT PROJECT
Amerada Hess (Thailand) Limited (AHT) plans to develop the Phu Horm gas field in Petroleum Concession Blocks E5N and EU-1 in Udonthani province in Northeastern Thailand. The key objective is to supply natural gas via pipeline to the Electricity Generating Authority of Thailand (EGAT) Nam Phong Power Plant. The operation is schedule to come on stream in late 2005 with a production capacity of 135 million standard cubic feet of gas per day (MMscfd)

TOPOGRAPHICAL SURVEY REPORT on PTT BAN RONG PO LPG TERMINAL PROJECT
PTT Public Company Limited, herein also called "PTT" engaged the services of Ten Consultants Co., Ltd. herein also called "TEN" to provide Topographical Survey for the PTT BAN RONG PO LPG TERMINAL PROJECT located in Banglamung, Chonburi, Thailand. TEN commenced his services since 23rd April 2019 and finished field topographical survey on 7th May 2019 Topographical survey was conducted to cover the Project Area of about 166,700 sq.m. (104 rai)

TOPOGRAPHICAL SURVEY REPORT on AVX MEGA PLANT, NAKORN RATCHASIMA PROJECT
VITA TEAM CONSULTANT CO., LTD. herein also called "VITA" engaged the services of Ten Consultants Co., Ltd., herein also called "TEN" to provide Topographical Survey for the AVX MEGA PLANT, NAKORN RATCHASIMA PROJECT located in Nava Nakorn Nakorn Ratchasima Industrial Zone, BOI Zone 3, Thailand. TEN commenced his services since 2nd August 2019 and finished field topographical survey on 4th August 2019.

Detailed Survey for PTTGC 30 km Existing Underground Gas Pipeline
As PTT Global Chemical Public Company Limited (PTTGC) has planned to rehabilitate its safety signs along the existing gas pipeline from its facilities in Map Ta Phut to Integrate Refinery & Petrochemical Complex (IRPC) in Rayong for a distance of about 30 kilometers, a detailed survey of the exact pipeline alignment buried underground and its crossing locations was required to be drawn on to the as-built maps and drawings.

Shell Update Plot Plan Project: 5 Terminals Topographic Survey
Ten Consultants Co., Ltd. was engaged by Foster Wheeler (Thailand) Limited to provide Topographic Survey for 5 terminals of Shell Update Plot Plan Project, the assigned terminals are followings; 1. Chongnonsi (CNS), 2. Khonkaen (KKN), 3. Lampang (LMP), 4. Suratthani (BND) and 5. Samut Songkhram (SSK).

TOPOGRAPHICAL SURVEY CFP-CRUDE OIL TANKS PROJECT (C-COT)
Foster Wheeler (Thailand) Limited engaged the service of "TEN" to provide a Topographic Survey for the CFP-CRUDE OIL TANKS PROJECT (C-COT) which is the Project of Thai Oil Public Company Limited, located in Thai Oil Refinery, Sriracha district, Chonburi province, Thailand.

WATER CRISIS PROJECT Site Survey & Soil Investigation
PTT Maintenance and Engineering Company Limited "PTTME" engaged the services of TEN to provide site survey (detailed topographic survey) and soil investigation services for the Water Crisis Project located in Map Taphut, Rayong province, Thailand.

Topographic survey and Geotechnical Investigation Services
TEN conducted a topographic survey for the PTT Public Company Limited 30" gas pipeline from Block Valve # 10 in Ratchburi province to RA#6 station in Nonthaburi province (so called "RRPP Project" for the distance of 120 kilometers for further engineering design and environmental impact assessment (by other).

TOPOGRAPHIC SURVEY for CFP PROJECT at Thai Oil Refinery
"TEN" provided a service of Topographic Survey of the Clean Fuel ''CFP" Project for Thai Oil located in Thai Oil Refinery, Sriracha district, Chonburi province. There are 2 areas were conducted the first one is Area A covering an area of 200 Rai and the second is Area B covering an area of 118 Rai with Alternate Route as the boundary and route.

Land Property Map and MOU Preparation for L15 Pipeline Tie-In
TEN was engage by APICO (Khorat) Limited to provide land property map and MOU preparation and topographic survey 10.5 km at tie-in site of L15 pipeline tie-in of Sin Phu Horm Gas Development Project where located in Undonthani province of THAILAND

Topographic survey including with land property map & MOU preparation along gas pipeline route of 2.7 km.
TEN was engage by APICO (Khorat) Limited to provide topographic survey including with land property map & MOU preparation along gas pipeline route of 2.7 km from PAD A well site to the proposed gas preparation plant (GPP) of Don Mun Gas Development Project where located in Kalasin province of THAILAND

PHU HORM GAS DEVELOPMENT PROJECT
Amerada Hess (Thailand) Limited (AHT) plans to develop the Phu Horm gas field in Petroleum Concession Blocks E5N and EU-1 in Udonthani province in Northeastern Thailand. The key objective is to supply natural gas via pipeline to the Electricity Generating Authority of Thailand (EGAT) Nam Phong Power Plant.

PTT PHENOL PROJECT
Phenol is mostly used in the production of certain plastic auto parts. Its demand is currently around 150,000 tons a year with annual demand growth of 6%. As the increase in domestic demand of phenol, PTT Phenol Co., Ltd. Is established to be the producer of phenol. The PTT Phenol plant will be situated on the land in Eastern Industrial Estate in Mab Ta Phut, Rayong Province. the Plant is planned to produce 200,000 tons of phenol per year and is scheduled to operate in the second quarter of the year 2007.

MINIBLAST OF YUAN INDUSTRIAL ESTATE (Presently: WHA Eastern Seaboard Industrial Estate)
The Miniblast Project Area is located on a hill of the difference of high and low ground elevations is about 30 meters. The highest point of the area is on the north nearby East Water Booster Station. The elevation around the place is about +77.000 m above mean sea level. The subsoil of the project area is mostly composed of medium dense to very dense clayey sand and hard to very stiff sandy clay. However, loose materials are also found in same areas.